A RAMP INSTALLATION COMPLETED IN LIGHT SNOW
The client required a ramp installed over the weekend from the main entrance ahead of Monday’s reopening.
Our in-house design team produced a detailed 3D model and 2D plan within 24 hours, providing the customer with comprehensive visualisations of the project.

The fitters completed the ramp in just a few hours despite unexpected light snow.
Unlike traditional concrete, which would have required several days to cure, our ramp was immediately ready for use after being fitted.
By working outside standard hours, we handed over on time with no disruption to the centre’s weekday opening.